The Public Works Authority, Ashghal, yesterday announced start of work on phase one of the road from Rawdat Rashed to Umm Garn which falls under its Local Roads and Drainage programme.
The 33km road which is perpendicular to Salwa Road faces a north direction; it also stretches past Rawdat Rashed area to Dukhan Road.
The project has been divided into five phases. Phase one includes construction of an 8.5km dual three-lane carriageway stretching from Salwa Road to a site near the existing entrance of Rawdat Rashed area. This phase is expected to be completed in Q2, 2016.
The second phase will include the construction of a 10.4km dual three-lane carriageway. The road starts from where phase one ended and stretches all the way to a new roundabout that will link to an existing road in Al Shahaniya, past Rawdat Rashed area. This phase is expected to be completed in Q2, 2016.
Ashghal is distributing flyers in both English and Arabic to residents with information on the project’s description and benefits as well as safety guidelines and how to get in touch with community officers responsible for this project.
Follow us on our social media channels:
@ILQlive
@ILQlive
@ILoveQtr
ILoveQatar
You have successfully registered your account!
Please confirm your e-mail address by clicking on the URL sent to you.The e-mail usually arrives in 5-10 minutes.How ajeeb was that!? Thanks for contributing to our community! Your post will appear after we take a quick look!